Planner

Fix schedule coverage faults

When a schedule shows Schedule Fault in the Schedules board, the coverage or checklist targets are preventing the system from calculating a next due date. Use the messages below to find the cause and fix it.

No matching coverage targets

The fault message says the schedule has coverage targets, but no in-service assets on this site match them yet.

Cause Coverage is attached to the schedule through asset classes, locations, or specific assets, but none of the linked targets are currently in service, or the schedule scope does not match any active assets.

Fix

  1. Check that the assets or locations attached to the schedule are active and in service.

  2. Link additional asset classes, asset definitions, or direct asset attachments to the schedule coverage.

  3. If the scope is too narrow, adjust the schedule coverage so it matches assets that exist on the site.

No checklist target match

The fault message says coverage rows exist, but none match a checklist target on this schedule.

Cause The schedule has coverage rows, but every row is skipped because there is no winning checklist target that applies to it. This usually means the checklist target scope is too restrictive for the attached coverage.

Fix

  1. Open the schedule and review the Checklist Targets section.

  2. Widen the target scope or add targets that match the assets or locations already in coverage.

  3. If the checklist targets are correct, remove or adjust the coverage rows that do not match any target.

Was this helpful?